Inspection Detail
Inspection: 1421828.015 - Triple D Communications, Llc
Inspection Information - Office: Toledo Area Office
Site Address:
Triple D Communications, Llc
21209 Caris Rd. (Across From)
Bowling Green, OH 43402
Mailing Address:
950 48th Avenue N. Suite 100, Myrtle Beach, SC 29577
Union Status: NonUnion
SIC:
NAICS: 238210/Electrical Contractors
Inspection Type: Referral
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 12/20/2019
Emphasis:
Case Closed: 06/12/2024
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Referral | 1483611 | Yes |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 5 | 5 | ||||
| Current Violations | 5 | 5 | ||||
| Initial Penalty | $56,261 | $0 | $0 | $0 | $0 | $56,261 |
| Current Penalty | $0 | $0 | $0 | $56,261 | $0 | $56,261 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Other | 19100268 B07 | 12/26/2019 | 12/15/2022 | $11,934 | $11,934 | $0 | 01/21/2020 | F - Formal Settlement | |
| 2. | 01002 | Other | 19100268 I01 | 12/26/2019 | 12/15/2022 | $11,934 | $11,934 | $0 | 01/21/2020 | F - Formal Settlement | |
| 3. | 01003 | Other | 19100268 J03 | 12/26/2019 | 12/15/2022 | $11,934 | $11,934 | $0 | 01/21/2020 | F - Formal Settlement | |
| 4. | 01004 | Other | 19100268 N11 IV | 12/26/2019 | 12/15/2022 | $8,525 | $8,525 | $0 | 01/21/2020 | F - Formal Settlement | |
| 5. | 01005 | Other | 19100332 B01 | 12/26/2019 | 12/15/2022 | $11,934 | $11,934 | $0 | 01/21/2020 | F - Formal Settlement |
Investigation Summary
At 11:30 a.m. on August 1, 2019, an employee worked with two coworkers to replace damaged utility poles and repair telecommunication lines. The employee used a vehicle mounted work platform to reach the location to conduct repairs while coworker 1 operated a digger derrick and coworker 2 acted as the grounds man. Upon reaching the work, the employee began to detach the sagging neutral circuit conductor and used mule tape to move the conductor out of the way of the location where the telecommunication cable would be installed. At some point, the employee's left hand contacted the seventy-two-hundred-volt primary line, and an arc flash occurred. The employee was hospitalized to treat electrical shock and burn injuries received.
Keywords: Burn, Electric Arc Flash, Electric Shock, Electrical Burn, Elevated Work Platform, Power Lines, Repair, Service Conductor, Telecom Work, Utility Pole
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 1421828.015 | 25 | M | Hospitalized injury | Electrical power installers and repairers |