Powered by GoogleTranslate

Violation Detail

Standard Cited: 19100119 J05 Process safety management of highly hazardous chemicals.

Inspection Nr: 1565223.015

Citation: 02003

Citation Type: Repeat

Abatement Status: Abatement Completed

Initial Penalty: $56,980.00

Current Penalty: $32,478.60

Issuance Date: 03/28/2022

Nr Instances: 13

Nr Exposed: 33

Abatement Date: 04/21/2022

Gravity: 5

Report ID: 0317300

Contest Date:

Final Order: 07/13/2022

Related Event Code (REC): R

Emphasis:

Substance: 0170


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 07/13/2022 $32,478.60 04/21/2022 Repeat  
Penalty Z: Issued 03/28/2022 $56,980.00 04/21/2022 Repeat  

Text For Citation: 02 Item/Group: 003 Hazard:

1910.119(j)(5): The employer did not correct deficiencies in equipment that are outside acceptable limits before further use or in a safe and timely manner when necessary means are taken to assure safe operation: a) House Engine Room: On or about 10/1/2021, the employer failed to clean, and paint corroded metal surfaces under layers of wet insulation and damaged vapor barrier and then replace the insulation and vapor barrier on Intercooler #4. A potential break along degraded metal surfaces results in loss of containment of ammonia in the system and employee exposure to ammonia via inhalation which can result in serious illness or death. b) FRIGO Engine Room: On or about 10/1/2021, the employer failed to clean, and paint corroded metal surfaces under layers of insulation and damaged vapor barrier and then replace the insulation and vapor barrier along a C-7 LSS pipe run. A potential break along this pipe run results in loss of containment of ammonia in the system and employee exposure to ammonia via inhalation which can result in serious illness or death. c) FRIGO Engine Room: On or about 10/1/2021, the employer failed to clean, and paint corroded metal surfaces under layers of insulation and damaged vapor barrier and then replace the insulation and vapor barrier along a C-7 LSS pipe run. A potential break along this pipe run results in loss of containment of ammonia in the system and employee exposure to ammonia via inhalation which can result in serious illness or death. d) House Engine Room: On or about 10/1/2021, the employer failed to clean, and paint corroded metal surfaces under layers of insulation and damaged vapor barrier and then replace the insulation and vapor barrier along a C-2 HSS pipe run. A potential break along this pipe run results in loss of containment of ammonia in the system and employee exposure to ammonia via inhalation which can result in serious illness or death. e) FRIGO Engine Room: On or about 10/1/2021, the employer failed to replace unsuitable Armaflex Insulation along a pipe run at the Oil Separator Cooler. A potential break along this pipe run results in loss of containment of ammonia in the system and employee exposure to ammonia via inhalation which can result in serious illness or death. f) House Engine Room: On or about 10/1/2021, the employer failed to replace pipe runs along the C-2 compressor suction header when ultrasonic testing (UT) indicated corrosion on this equipment beyond the 10% degradation threshold for replacement. A potential break along this pipe run results in loss of containment of ammonia in the system and employee exposure to ammonia via inhalation which can result in serious illness or death. g) House Engine Room: On or about 10/1/2021, the employer failed to replace Intercooler-4 pipe runs along a coil out vertical nipple on one and a quarter inch piping (sample ID 2) on the tank when ultrasonic testing (UT) indicated corrosion on this equipment beyond the 10% degradation threshold for replacement. A potential break along this pipe run results in loss of containment of ammonia in the system and employee exposure to ammonia via inhalation which can result in serious illness or death. h) House Engine Room: On or about 10/1/2021, the employer failed to replace Intercooler-4 pipe runs along a coil in nipple on tank one and a quarter inch piping (sample ID 3) on the tank when ultrasonic testing (UT) indicated corrosion on this equipment beyond the 10% degradation threshold for replacement. A potential break along this pipe run results in loss of containment of ammonia in the system and employee exposure to ammonia via inhalation which can result in serious illness or death. i) FRIGO Engine Room: On or about 10/1/2021, the employer failed to replace pipe runs along the freezer e-pump receiver minimum flow piping, the top and bottom nipples on the mushroom suction trap level column, and a five-inch horizontal length of pipe on EC-1 area piping where EC-8 west and EC-8 east condenser drain piping meet before draining into the HPR-1when ultrasonic testing (UT) indicated corrosion on this equipment beyond the 10% degradation threshold for replacement. A potential break along these pipe runs results in loss of containment of ammonia in the system and employee exposure to ammonia via inhalation which can result in serious illness or death. j) House Engine Room: On or about 10/1/2021, the employer failed to replace Intercooler-4 pipe runs along a coil out vertical nipple on one and a quarter inch piping (sample ID 1) on the tank when ultrasonic testing (UT) indicated corrosion on this equipment beyond the 10% degradation threshold for replacement. A potential break along this pipe run results in loss of containment of ammonia in the system and employee exposure to ammonia via inhalation which can result in serious illness or death. k) FRIGO Engine Room: On or about 10/1/2021, the employer failed to keep the FRIGO oil separator cooler free from excessive ice buildup, potentially hindering the operation of a safety relief valve, exposing employees to loss of containment of ammonia in the system and exposure to ammonia via inhalation which can result in serious illness or death. l) House Engine Room: On or about 10/1/2021, the employer failed to keep the Intercooler-4 Oil Pot (on the pump pack) free from excessive ice buildup, potentially hindering the operation of a safety relief valve, exposing employees to loss of containment of ammonia in the system and exposure to ammonia via inhalation which can result in serious illness or death. m) House Engine Room: On or about 10/1/2021, the employer failed to keep the C-9 LIC line from excessive ice buildup. This ice buildup has the potential to inhibit access and operation to valves and, to result in damage to equipment due to the ice's shear weight, exposing employees to loss of containment of ammonia in the system and exposure to ammonia via inhalation which can result in serious illness or death. Hanover Foods Corporation was previously cited for a violation of this Occupational Safety and Health Standard, its equivalent, or essentially similar standard , 29 CFR 1910.119(j)(5), which was contained in OSHA inspection number 1390093, citation number 1, item number 2 and was affirmed as a final order on 5/11/2020, with respect to a workplace located at 7000 Millington Road, Clayton, DE 19938. Pursuant to 29 CFR 1903.19, the employer must submit abatement certification and documentation, required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.