Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1571943.015
Citation: 02002A
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/27/2022
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity:
Report ID: 0936400
Contest Date:
Final Order: 06/06/2022
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/06/2022 | $0.00 | Other | ||
| Penalty | Z: Issued | 04/27/2022 | $0.00 | Other |
Text For Citation: 02 Item/Group: 002A Hazard:
29 CFR 1910.147(c)(6)(i):The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: DELINTING CENTRIFUGE: A review of the energy control procedures had not been completed annually to ensure proper procedures were followed. The last review occurred in March 2019.