Violation Detail
Standard Cited: 19100147 D The control of hazardous energy (lockout/tagout).
Inspection Nr: 1562262.015
Citation: 02001A
Citation Type: Repeat
Abatement Status: Abatement Completed
Initial Penalty: $145,027.00
Current Penalty: $145,000.00
Issuance Date: 04/22/2022
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 09/13/2023
Gravity: 10
Report ID: 0521700
Contest Date: 05/13/2022
Final Order: 12/21/2023
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 12/21/2023 | $145,000.00 | 09/13/2023 | Repeat | |
| Penalty | C: Contested | 05/13/2022 | $145,027.00 | 05/18/2022 | Willful | |
| Penalty | Z: Issued | 04/22/2022 | $145,027.00 | 05/18/2022 | Willful |
Text For Citation: 02 Item/Group: 001A Hazard:
29 CFR 1910.147(d): The established procedure for the application of energy control (the lockout or tagout procedures) did not cover the actions listed in and was not done in sequence as required by 29 CFR 1910.147(d)(1)-(6): a) Phase 4, Production Line 16 - On or about October 30, 2021, employees were exposed to machine hazards associated with moving parts and in-going nip points while servicing and maintaining the RP-16 Kliklok Vari-Straight Topload Carton Closer, serial no. VS-192/A0338. The employer failed to implement energy control application steps as the machine was not shut down or turned off to perform the servicing work [per the 1910.147(d)(2) requirements]. As a result, the remaining applicable energy control elements, involving machine isolation [(d)(3)], LOTO device application [(d)(4)], dissipation of residual energy [(d)(5)((i)], and verification of isolation [(d)(6)], were not implemented to protect employees from machine servicing hazards.