Standard Cited: 19100219 F03 Mechanical power-transmission apparatus.
Inspection Nr: 1490080.015
Citation: 01004C
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 11/20/2020
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 12/28/2020
Gravity: 5
Report ID: 0316700
Contest Date:
Final Order: 12/16/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 11/20/2020 | $0.00 | 12/28/2020 | Serious |
Text For Citation: 01 Item/Group: 004C Hazard:
29 CFR 1910.219(f)(3): Sprocket wheels and chains which were seven (7) feet or less above floors or platforms were not enclosed: (a) Timber Mat Jigs, Lower, Western Side of 60 x 120 Building - Employees used a custom-made A-frame hydraulic-powered horizontal drill rig, to drill holes across the width of the wood timbers that make up the timber mats. This drill rig did not have machine guarding to protect the operator from the floor level chain and sprockets, on or about August 24, 2020. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and state employees and their representatives were informed of this abatement.