Violation Detail
Standard Cited: 19100269 M03 VI Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1475244.015
Citation: 01004B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/03/2020
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 07/01/2020
Gravity: 5
Report ID: 0636900
Contest Date: 08/24/2020
Final Order: 09/23/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 09/23/2020 | $0.00 | 07/01/2020 | Serious | |
| Penalty | C: Contested | 08/24/2020 | $0.00 | 07/01/2020 | Serious | |
| Penalty | Z: Issued | 06/03/2020 | $0.00 | 07/01/2020 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard:
29 CFR 1910.269(m)(3)(vi): 29 CFR 1910.269(m)(3)(vi): After the applicable requirements in paragraphs (m)(3)(i) through (m)(3)(v) of this section have been followed and the system operator gives a clearance to the employee in charge, the employer did not ensure that the lines and equipment are deenergized by testing the lines and equipment to be worked with a device designed to detect voltage: At a site located at 1314 FM 1768, Olney, Texas; the employer gave clearance for employees to perform work on the left side of the PDP electrical panel at 690-volts and did not inform them of lines and equipment not de-energize. The employees were exposed to electrical arc flash.