Violation Detail
Standard Cited: 19100269 M03 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1475244.015
Citation: 01004A
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $5,398.00
Current Penalty: $5,398.00
Issuance Date: 06/03/2020
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 07/01/2020
Gravity:
Report ID: 0636900
Contest Date: 08/24/2020
Final Order: 09/23/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 09/23/2020 | $5,398.00 | 07/01/2020 | Other | |
| Penalty | C: Contested | 08/24/2020 | $5,398.00 | 07/01/2020 | Serious | |
| Penalty | Z: Issued | 06/03/2020 | $5,398.00 | 07/01/2020 | Serious |
Text For Citation: 01 Item/Group: 004A Hazard:
29 CFR 1910.269(m)(3)(iii): The employer shall ensure that automatically and remotely controlled switches that could cause the opened disconnecting means to close are also tagged at the points of control. The employer shall render the automatic or remote control feature inoperable, unless its design does not so permit. At a site located at 1314 FM 1768, Olney, Texas; the employer failed to tag out the left side of the PDP of 690-volts still energized prior to allowing employees to perform electrical work. The employees were exposed to arc flash hazards.
Translate