Standard Cited: 19100184 E03 I Slings.
Inspection Nr: 330648.015
Citation: 01003
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $3,500.00
Current Penalty: $3,150.00
Issuance Date: 09/14/2012
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 10/15/2012
Gravity:
Report ID: 0729700
Contest Date:
Final Order: 10/09/2012
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 10/09/2012 | $3,150.00 | 10/15/2012 | Other | |
| Penalty | Z: Issued | 09/14/2012 | $3,500.00 | 10/15/2012 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.184(e)(3)(i): A thorough periodic inspection of alloy steel chain slings was not made on a regular basis and/or were done at intervals greater than once every 12 months: At the establishment employee(s) using an alloy steel sling#NK54239-A to position the all purpose vehicle frame at station 1 on the assembly line were exposed to crushing hazards due to no periodic inspection of the alloy steel chain sling being performed to lift an all purpose vehicle frame that weigh approximately 4,104 pounds.