Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1396190.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,282.00
Current Penalty: $4,875.00
Issuance Date: 06/07/2019
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 08/01/2019
Gravity: 10
Report ID: 0936200
Contest Date:
Final Order: 06/28/2019
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/28/2019 | $4,875.00 | 08/01/2019 | Serious | |
| Penalty | Z: Issued | 06/07/2019 | $9,282.00 | 06/19/2019 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: Naval OLF NEX: On April 23, 2019, employee(s) were repairing a wireless pressurized line leak detector (WPLLD) in a fuel sump while the equipment was energized. The WPLLD broke and fuel sprayed from the equipment. Employee(s) manually disengaged the yolk assembly to isolate the energy, which ignited the fuel vapors, and created a flash fire. De-energization of the fuel pump was not achieved prior to performing maintenance on the fuel sump system. Employees were exposed to fire and/or explosion hazards.