Violation Detail
Standard Cited: 19260600 A06 IV Equipment.
This violation item has been deleted.
Inspection Nr: 1250811.015
Citation: 01003
Citation Type: Serious
Abatement Status: Not Completed - AD Discretion
Initial Penalty: $12,675.00
Current Penalty: $0.00
Issuance Date: 12/12/2017
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 01/04/2018
Gravity: 10
Report ID: 0636900
Contest Date:
Final Order: 01/04/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/04/2018 | $0.00 | 01/04/2018 | Serious | |
| Penalty | Z: Issued | 12/12/2017 | $12,675.00 | 01/04/2018 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.600(a)(6)(iv): A person was not designated to observe clearance of the equipment and give timely warning for all operations where it is difficult for the operator to maintain the desired clearance by visual means. At the construction site, the employer did not have a person designated to observe clearance of overhead power lines and did not have any other means to give timely warnings for operations where it was difficult for the operators of a John Deere 650DLC excavator and a Caterpillar 326FL excavator to maintain the desired clearances exposing employees to electrocution hazards.