Standard Cited: 19100107 D12 Spray finishing using flammable and combustible materials.
Inspection Nr: 1398943.015
Citation: 01002B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/21/2019
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 09/17/2019
Gravity:
Report ID: 0728500
Contest Date:
Final Order: 09/17/2019
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/17/2019 | $0.00 | 09/17/2019 | Other | |
| Penalty | Z: Issued | 08/21/2019 | $0.00 | 09/17/2019 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.107(d)(12): Freshly sprayed articles were dried only in spaces not provided with adequate ventilation to prevent the formation of explosive vapors: On April 27, 2019 at the worksite located at 1016 Progress Street, Mount Vernon, Missouri 65712, employees were exposed to serious fire and explosion hazards. The freshly sprayed tank was left to dry in a space which was not provided with adequate ventilation to prevent the formation of explosive vapors.