Violation Detail
Standard Cited: 19100212 A03 II General requirements for all machines.
Inspection Nr: 1487939.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,096.00
Current Penalty: $3,500.00
Issuance Date: 10/07/2020
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 11/03/2020
Gravity: 5
Report ID: 0316700
Contest Date:
Final Order: 11/04/2020
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/04/2020 | $3,500.00 | 11/03/2020 | Serious | |
| Penalty | Z: Issued | 10/07/2020 | $8,096.00 | 11/03/2020 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.212(a)(3)(ii): Point of operation guards were not designed and constructed as to prevent the operator from having any part of their body in the danger zone during the operating cycle: (a) Machining Department - Employees used two Whirlwind, model 212, cut-off saws, known as Saw #1 and Saw #2, to cut long plastic boards into smaller uniform length pieces. These saws did not have complete point of operation guards in that both saws' clamp/guard assemblies were missing the front shields, exposing employees to contact with rotating saw blades, on or about August 11, 2020. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and state employees and their representatives were informed of this abatement.