Violation Detail
Standard Cited: 19100147 C06 I C The control of hazardous energy (lockout/tagout).
Inspection Nr: 1405247.015
Citation: 01002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $7,577.00
Current Penalty: $4,540.00
Issuance Date: 07/02/2019
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 10/01/2019
Gravity:
Report ID: 0418100
Contest Date:
Final Order: 07/18/2019
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/18/2019 | $4,540.00 | 10/01/2019 | Other | |
| Penalty | Z: Issued | 07/02/2019 | $7,577.00 | 08/19/2019 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i)(C): Where lockout was used for energy control, the periodic inspection did not include a review, between the inspector and each authorized employee, of that employee's responsibilities under the energy control procedure being inspected. On 6/4/19, at the Macon facility, the employer did not ensure the periodic inspection of the Lockout program included all authorized employees.