Violation Detail
Standard Cited: 19100179 N03 I Overhead and gantry cranes.
Inspection Nr: 1546221.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/07/2022
Nr Instances: 1
Nr Exposed: 5
Abatement Date:
Gravity: 10
Report ID: 0521100
Contest Date:
Final Order: 01/25/2022
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/25/2022 | $0.00 | Serious | ||
| Penalty | Z: Issued | 01/07/2022 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.179(n)(3)(i): Handling the load. Moving the load. The load shall be well secured and properly balanced in the sling or lifting device before it is lifted more than a few inches. On July 18, 2021 at 2901 Sherman Street in Wausau, Wisconsin, an employee was lifting an I-beam approximately four inches with an overhead crane when the beam separator hook device released from the end of the I-beam dropping it.