Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1500330.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/13/2021
Nr Instances: 1
Nr Exposed: 300
Abatement Date: 04/23/2021
Gravity: 5
Report ID: 0317900
Contest Date:
Final Order: 05/11/2021
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/11/2021 | $0.00 | 04/23/2021 | Serious | |
| Penalty | Z: Issued | 04/13/2021 | $0.00 | 04/23/2021 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(c)(6)(i):The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: (a) Aquaflex Press Room: On or about October 29, 2020, employees performed maintenance and servicing on various plant machinery that has multiple sources of energy, but employer did not conduct a periodic inspection of the energy control procedure within the last 12 months to ensure that the procedure and the requirement of this standard were being followed.