Violation Detail
Standard Cited: 19100269 N05 Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1452177.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/16/2020
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 04/07/2020
Gravity: 5
Report ID: 0419400
Contest Date:
Final Order: 04/02/2020
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/02/2020 | $0.00 | 04/07/2020 | Serious | |
| Penalty | Z: Issued | 03/16/2020 | $0.00 | 04/07/2020 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.269(n)(5): The employer did not ensure employees tested line and equipment to verify the absence of nominal voltage before installing grounds when previously installed grounds were not present. (a) Pole with Tag 336-04-34 - On or about December 17, 2019 the employer did not ensure employees had tested the line to ensure it was deenergized prior to starting work, exposing employees to electrical shocks.