Violation Detail
Standard Cited: 19100119 D03 I B Process safety management of highly hazardous chemicals.
Inspection Nr: 1400751.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/11/2019
Nr Instances: 1
Nr Exposed: 15
Abatement Date: 12/02/2019
Gravity: 1
Report ID: 0625400
Contest Date:
Final Order: 01/21/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/21/2020 | $0.00 | 12/02/2019 | Serious | |
| Penalty | Z: Issued | 10/11/2019 | $0.00 | 12/02/2019 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.119(d)(3)(i)(B): The employer's piping and instrument diagrams were not accurate and did not represent equipment that was existing and was part of the process. On or about 14 May 2019, and at times prior thereto, the piping and instrumentation diagram for unit H-201 Crude Charge Heater was not up-to-date and did not indicate the addition of two Maxon valves from August 2014.