Violation Detail
Standard Cited: 19100269 M03 VI Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1766030.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $16,550.00
Current Penalty: $9,930.00
Issuance Date: 01/28/2025
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 03/03/2025
Gravity: 10
Report ID: 0830500
Contest Date:
Final Order: 02/19/2025
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/19/2025 | $9,930.00 | 03/03/2025 | Serious | |
| Penalty | Z: Issued | 01/28/2025 | $16,550.00 | 03/03/2025 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(m)(3)(vi): After the applicable requirements in paragraphs (m)(3)(i) through (m)(3)(v) of this section have been followed and the system operator gives a clearance to the employee in charge, the employer did not ensure that the lines and equipment are deenergized by testing the lines and equipment to be worked with a device designed to detect voltage: (a)Hooper Corporation at transmission line structure No. 31, Southwest Pole, Empire, CO 80438: On or about July 29, 2024, the employer did not ensure that the electrical transmission line that was energized at 115kV was de-energized prior to two employees being flown into position from a helicopter long-line to replace a static dampener on the ground line above it. During the process of replacing the dampener the two employees sustained serious electric shock and burn injuries. One of the employees died from his injuries.