Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1666488.015
Citation: 01001
Citation Type: Other
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $4,688.00
Current Penalty: $3,600.00
Issuance Date: 08/14/2023
Nr Instances: 2
Nr Exposed: 2
Abatement Date: 09/08/2023
Gravity: 10
Report ID: 0728900
Contest Date: 09/07/2023
Final Order: 12/02/2023
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 12/02/2023 | $3,600.00 | 09/08/2023 | Other | |
| Penalty | C: Contested | 09/07/2023 | $4,688.00 | 09/08/2023 | Serious | |
| Penalty | Z: Issued | 08/14/2023 | $4,688.00 | 09/08/2023 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolding was not fully planked or decked: Employees engaged in window replacement and upgrade on a residential home located at 2536 South 191st Circle, Omaha, Nebraska, were exposed to fall hazards in that two sets of scaffolding employees were working on were not fully planked as required by this sub-part.