Violation Detail
Standard Cited: 19100181 I03 III B Derricks.
Inspection Nr: 1626725.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $15,625.00
Current Penalty: $15,625.00
Issuance Date: 03/10/2023
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 07/03/2023
Gravity: 10
Report ID: 0627700
Contest Date:
Final Order: 04/06/2023
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/06/2023 | $15,625.00 | 07/03/2023 | Other | |
| Penalty | Z: Issued | 03/10/2023 | $15,625.00 | 04/05/2023 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.181(i)(3)(iii)(b):During hoisting, care was not taken that: the load did not contact any obstructions. On or about October 05, 2022, the employer did not ensure the suspended drill string could not contact any obstruction, exposing employees to struck by hazards.