Violation Detail
Standard Cited: 19100269 D02 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1597063.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $14,502.00
Current Penalty: $10,151.40
Issuance Date: 11/17/2022
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 12/20/2022
Gravity: 10
Report ID: 0418800
Contest Date:
Final Order: 12/18/2022
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/18/2022 | $10,151.40 | 12/20/2022 | Serious | |
| Penalty | Z: Issued | 11/17/2022 | $14,502.00 | 12/14/2022 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(d)(2)(iii): Procedures were not developed, documented, and used for the control of potentially hazardous energy covered by paragraph (d) of this section: On or about May 19th, 2022, at FPL South Area Transmission Service Center at 14700 NW 41st Street in Doral, Florida, employees were exposed to struck-by and pressure discharge when written procedures were not used for depressurizing the SF6 breaker.