Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1595787.015
Citation: 01001
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $4,351.00
Current Penalty: $1,000.00
Issuance Date: 07/21/2022
Nr Instances: 1
Nr Exposed: 1
Abatement Date:
Gravity: 1
Report ID: 0728900
Contest Date: 08/12/2022
Final Order: 01/27/2023
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 01/27/2023 | $1,000.00 | Other | ||
| Penalty | C: Contested | 08/15/2022 | $4,351.00 | Serious | ||
| Penalty | Z: Issued | 07/21/2022 | $4,351.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports as follows: Platform(s) on all working levels of scaffolds, were not fully planked or decked between the front uprights and guardrail supports such that the space between adjacent units, and the space between the platform and the uprights. The employer failed to protect employees from fall hazards. This was most recently documented on or about May 13th, 2022, in Gretna, Nebraska 68028. The side brackets that were attached to the Hydro Mobile scaffolding were not fully planked.