Violation Detail
Standard Cited: 19100147 F01 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1574797.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $9,324.00
Current Penalty: $9,324.00
Issuance Date: 07/15/2022
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 03/01/2023
Gravity: 5
Report ID: 0626700
Contest Date:
Final Order: 08/26/2022
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/26/2022 | $9,324.00 | 03/01/2023 | Other | |
| Penalty | Z: Issued | 07/15/2022 | $9,324.00 | 08/10/2022 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(f)(1)(ii): When lockout or tagout devices temporarily were removed from the energy isolating device and the machine or equipment was energized to test or position the machine, the employees were not removed from the machine or equipment area in accordance to the paragraph (e)(2): a) On or about January 19, 2022 an employee was not safely positioned when troubleshooting a fan belt noise on a Multiquip 60Kw Power Generator.