Violation Detail
Standard Cited: 19100147 C04 II C The control of hazardous energy (lockout/tagout).
Inspection Nr: 1542384.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 09/29/2021
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 10/26/2021
Gravity:
Report ID: 0316700
Contest Date:
Final Order: 10/26/2021
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 09/29/2021 | $0.00 | 10/26/2021 | Other |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii)(C):The energy control procedure did not clearly and specifically outline the steps for placement, removal and transfer of lockout devices or tagout devices and the responsibility for them: a) SPROUT 615 PELLET MILL - The energy control procedure for the Sprout 615 Pellet Mill described multiple lock out points for multiple functions of the machine and did not specify which lock out point to utilize, on or about July 16, 2021. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.