Standard Cited: 19100147 C04 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1491965.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,096.00
Current Penalty: $2,867.20
Issuance Date: 02/05/2021
Nr Instances: 9
Nr Exposed: 6
Abatement Date: 03/29/2021
Gravity: 10
Report ID: 0521100
Contest Date:
Final Order: 02/23/2021
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/23/2021 | $2,867.20 | 03/29/2021 | Serious | |
| Penalty | Z: Issued | 02/05/2021 | $4,096.00 | 03/29/2021 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii): The procedures shall clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, and the means to enforce compliance including, but not limited to, the following: The energy control procedures utilized for de-energizing the mechanical power presses (Press #2, 3, 4, 5, 6, 8,9, 10, 13) did not include specific procedural steps to ensure the flywheel came to a complete stop, press slide positioned at bottom dead center of its stroke, air pressure was discharged and turned off and locked, and the spring pressure was neutralized.