Violation Detail
Standard Cited: 19100147 D06 The control of hazardous energy (lockout/tagout).
This violation item has been deleted.
Inspection Nr: 1438553.015
Citation: 01001
Citation Type: Serious
Abatement Status:
Initial Penalty: $13,494.00
Current Penalty: $0.00
Issuance Date: 04/09/2020
Nr Instances: 1
Nr Exposed: 8
Abatement Date: 05/27/2020
Gravity: 10
Report ID: 0626700
Contest Date: 05/05/2020
Final Order: 05/31/2021
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 05/31/2021 | $0.00 | 05/27/2020 | Serious | |
| Penalty | C: Contested | 05/07/2020 | $13,494.00 | 05/27/2020 | Serious | |
| Penalty | Z: Issued | 04/09/2020 | $13,494.00 | 05/27/2020 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(d)(6): Prior to starting work on machines or equipment that had been locked out or tagged out, the authorized employee did not verify that isolation and de-energization of the machine or equipment had been accomplished: a) On or about October 17, 2019, in the Maya Structure-I at Shell Deer Park Refinery, the employer failed to ensure the 200# steam system was isolated and blinded-off before they began work on the Motor Operator Valves (MOV).